Thomas Drive Resurfacing Project

Posted on: January 6, 2020

Thomas Drive Resurfacing Project Updates

Thomas drive resurfacing work picture

Update: July 6, 2020

Current Traffic impacts

The eastbound lanes of Thomas Drive are closed from approximately Crescent Drive to Bonita Street. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway).

The speed limit in the work zone is reduced to 25 mph.

Construction activities

During the week ending July 5, the following work was performed.

  • Completed placement of eight-inches of base lime rock for the Thomas Drive eastbound travel lanes between Tarpon Street and Crescent Drive.
  • Began grading lime rock base to the final template.
  • Investigated drainage obstructions and made needed repairs.

In observance of the July 4th holiday, no work was performed Thursday, July 2 through Sunday, July 5.

Work scheduled for the coming week includes:

  • Continue preparing the lime rock base, then paving the eastbound roadway between Sabine and Snapper Streets.
  • Adjusting water valves in the outside shoulders in advance of milling and paving.

Thomas drive resurfacing work picture

 A crew works to grade and compact the lime rock base for the Thomas Drive eastbound lanes between Tarpon Street and Crescent Drive.

Update: June 15, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive are closed from approximately Crescent Drive to Bonita Street. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway). The speed limit in the work zone is reduced to 25 mph.

Construction activities

 During the week ending June 14, the construction team undertook the following tasks.

  • Graded the soil stabilization materials to a final template and placed eight-inches of lime rock base for the eastbound travel lanes between Crescent Drive and Walnut Street.
  • Cleared and grubbed in advance of constructing trolley stops on the north and south sides of Thomas Drive at Holiday Drive.
  • Injected grout around conduits in new cast-in-place drainage structures.
  • Injected grout into the existing drainage system at 35 points between Benbow and Xavier Streets. Before and after video inspection was also performed at these locations.

A media availability period was provided Friday, June 12 to highlight the completion of paving the parking lot at S. Richard Seltzer Park parking. Commissioner Griffitts discussed the work with representatives of WJHG-TV, WMBB-TV, and the Panama City News Herald.  All three media outlets filed stories about the construction milestone that referenced the work as part of the county’s Half-Cent infrastructure surtax.

Work scheduled for the coming week includes:

  • Continuing soil stabilization efforts for the eastbound travel lanes between Crescent Drive and Bonita Street, as well as placing eight-inches of lime rock on sections already stabilized.
  • Constructing trolley stops at Holiday Road.
  • Continue grout injections for defective joints in the existing drainage system.
  • Installing cast-in-place tops for new drainage structures.
  • Continuing drainage system repairs/replacements.

  Thomas drive resurfacing work picture

Stabilization materials are graded for the Thomas Drive eastbound travel lanes between Crescent Drive and Walnut Street.

 Thomas drive resurfacing work picture

 A subcontractor injects grout into defective drainage system joints along Thomas Drive.

 Update: June 1, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive are closed from approximately Crescent Drive to Bonita Street. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway). The speed limit in the work zone is reduced to 25 mph.

Construction activities

During the week ending May 31, the construction team focused on the following activities.

Milling the Thomas Drive eastbound travel and median turn lanes between Venus and Snapper Streets.

  • Constructed through-lane access points along Thomas Drive eastbound between Venus and Snapper Streets to accommodate driveways and side streets.
  • Soil stabilization between Raven Street and Nancee Drive.
  • Grading lime rock base to the final template for the Rick Seltzer Park parking lot.
  • Removing drainage obstructions in advance of replacing the structures between Venus and Snapper Streets.

On the schedule this week is:

  • Additional milling of the eastbound travel and median turn lanes between Venus and Snapper Streets.
  • Mixing and sampling stabilized materials for the eastbound lanes between Crescent Drive and Bonita Street.
  • Removing drainage obstructions, along with forming and constructing cast-in-place walls for new drainage structures.

Rick Seltzer Park

Rick Seltzer Park is currently closed so the parking lot can be paved. Weather permitting, the contractor plans to stripe the new pavement this week so the park can be reopened.

  Workers doing the Thomas Dr Resurfacing Project

A crew of workers pours a concrete, cast-in-place drainage structure on Thomas Drive. Repair and replacement of damaged
drainage structures is a component of the $8.3-million Thomas Drive improvement project.

 Workers doing the Thomas Dr Resurfacing Project
A milling machine removes the existing asphalt pavement from the eastbound travel lanes of Thomas Drive near Venus Street.

Update: May 26, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive are closed from approximately Crescent Drive to Bonita Street. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway). The speed limit in the work zone is reduced to 25 mph.

Construction activities

During the week ending May 24, the construction team focused on the following activities.

  • Milling the eastbound travel lanes and median turn lanes to a depth of 11-inches between Crescent Drive and Venus Street.
  • Constructing driveway and side street access points between Crescent Drive and Venus Street.
  • Mixing and sampling subgrade materials for the eastbound travel lanes from Crescent Drive to Raven Street.
  • Removing existing drainage obstructions between Raven and Quarts Streets.

This week the construction team plans to:

  • Mill the eastbound travel lanes and median turn lanes between Crescent and Bonita Streets, and continue with mixing, sampling, and stabilizing subgrade material.
  • Remove drainage obstructions between Raven and Quarts Streets, then form and pour cast-in-place concrete components for new drainage structures.
  • Inject grout into defective joints in the existing drainage system throughout the project limits.

  Thomas Dr Resurfacing Project A milling machine removes asphalt from the Thomas Drive eastbound travel lanes near the Summerhouse Condominiums, 6505 Thomas Drive.

 Update: May 13,2020

Construction crews plan to shift Thomas Drive east and westbound traffic, between Holiday and Crescent drives, to the eastbound travel lanes Thursday, May 14. The traffic shift will allow milling, resurfacing and drainage improvements to continue for the westbound travel lanes.

Thomas Drive is the focus of an $8.3 million construction effort to resurface the roadway and make drainage improvements between Bristol Street and Joan Avenue.

Update: May 4, 2020

Current traffic impacts

 The westbound lanes of Thomas Drive are closed from approximately Venus Street to Biltmore Drive. Two-way traffic (one lane in each direction) is being maintained on the eastbound lanes (i.e., the southern half of the roadway).

The speed limit in the work zone is reduced to 25 mph.

Construction activities

 During the reporting period that ended Sunday, May 3, the prime contractor completed placement of lime rock base materials from east of Quarts Street to Biltmore Drive. In addition, lime rock base was prepared for the area immediately west of Quarts Street.

Meantime, cast-in-place wall components were constructed for replacement of removed/damaged drainage structures and tops.

Plans for the week ahead call for continuing placement of the needed eight-inches of lime rock base materials between Sabine and Quarts Streets. Pending the completion of drainage activities, crews further plan to complete the required stabilization in this area.

Repair/replacement of concrete drainage structures will also continue within the work zone.

Thomas drive resurfacing work pictureThomas Drive construction crews work to form the top for a new concrete drainage structure. Damaged drainage structures are being repaired or replaced as part of the $8.3 million improvement project underway between Joan Avenue and Bristol Street. Work is
currently estimated for completion this summer.

Thomas drive resurfacing work picture

A grading machine works near Biltmore Drive to stabilize lime rock for the base of the new Thomas Drive westbound travel lanes. The base will include eight-inches of lime rock. The material is frequently used in this area for road construction because it is in large supply and drains well. Completion of the Thomas Drive improvement project is currently estimated for this summer.

Update: April 27, 2020

Current traffic impacts

 The westbound lanes of Thomas Drive are closed from approximately Venus Street to Biltmore Drive. Two-way traffic (one lane in each direction) is being maintained on the eastbound lanes (i.e., the southern half of the roadway).

The speed limit in the work zone is reduced to 25 mph.

Construction activities

During the week ending April 26, 2020 crews completed stabilization of the westbound travel lanes and began placing eight-inches of lime rock base from east of Quarts Street to Venus Street.

New drainage structures were constructed in the westbound lanes (between Venus and Raven Streets) to replace damaged structures that were previously removed. The team also desilted and applied high-strength grout to four existing drainage structures.

In the week ahead the construction team will continue placing base lime rock on stabilized sections. In addition, stabilization and lime rock installation is planned between Quarts and Sabine Streets, as well as a 1,000-foot section near Crescent Drive.

Drainage work will include forming and constructing cast-in-place walls for new structures between Sabine and Quarts Streets.


 Thomas Drive Resurfacing workA crew member works to construct a cast-in-place wall for a new drainage structure along Thomas Drive

 Thomas Drive Resurfacing workCrews mixing and compacting Type B Stabilization between Raven and Quarts Streets.


Update: April 2, 2020

Current traffic impacts

The westbound lanes of Thomas Drive are closed from approximately Crescent Drive to Biltmore Drive. Two-way traffic (one lane in each direction) is being maintained on the eastbound lanes (i.e., the southern half of the roadway).

The speed limit in the Thomas Drive work zone is reduced to 25 mph.

Construction activities

For the week ending March 29, 2020, RARI paved the eastbound travel lanes, outside shoulder, and median turn lanes from west of Crescent Drive to Biltmore Drive. A traffic shift was implemented that moved two-way traffic to these newly paved travel lanes.

Additional paving included an isolated area of the eastbound lanes between Spyglass Drive and Benbow Street.

Emerald Coast Milling, a subcontractor to RARI, milled the remaining portion of the median turn lanes and outside shoulders between Spyglass and Crescent Drives.

DJI_0034


 Update: March 26, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive (i.e., the southern half of the four-lane roadway) are closed from approximately Raven Street to Silver Avenue. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway).

The speed limit in the Thomas Drive work zone is reduced to 25 mph.

Construction activities

The westbound travel lanes have been milled and resurfaced between Spyglass Drive and Biltmore Drive. 

During the past week work focused on the eastbound lanes from Biltmore Drive to east of Raven Street. Crews placed eight-inches of lime rock base, milled the outside shoulder, and placed 1.5-inches of structural asphalt. A small section of the eastbound roadway was also completed just west of Spyglass Drive.

All structural asphalt has now been placed for the eastbound travel lanes from east of Raven Street to Spyglass Drive.

New pavement striping was applied to the eastbound travel lanes on Thursday, March 26. This will allow traffic to be shifted so that resurfacing and drainage work can continue on the northern half of the four-lane roadway. The traffic shift is currently scheduled for Friday, March 27.

Thomas Drive Resurfacing 3-26 imageA Paving Crew works to apply 1.5-inches of new structural asphalt to the Thomas Drive eastbound
travel lanes near the Mariner East Condominium.


Update: March 6, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive (i.e., the southern half of the four-lane roadway) are closed from approximately Raven Street to Silver Avenue. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway).

Construction activities

The first lift of asphalt has been applied to the westbound lanes between Silver and Biltmore Avenues.

Milling and soil stabilization work is underway for the eastbound lanes between the Summerhouse Condominium, 6505 Thomas Drive (near Raven Street) and Biltmore Avenue. Crews are also repairing and replacing damaged drainage structures.

The speed limit in the work zone is reduced to 25 mph

Thomas drive resurfacing work pictureA paving crew works to resurface the Thomas Drive median

Thomas drive resurfacing work pictureSoil stabilization underway for the Thomas Drive westbound travel lanes near Mystic Street.

Thomas drive resurfacing work picture


Update: February 27, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive (i.e., the southern half of the four-lane roadway) are closed from Crescent Drive to Silver Avenue. Two-way traffic (one lane in each direction) is being maintained on the westbound lanes (i.e., the northern half of the roadway).

Traffic is expected to remain in this configuration for the next few weeks. The speed limit between Joan Avenue and Silver Avenue is 25 mph.

Construction activities

Paving is complete for the westbound lanes between Silver and Biltmore Avenues. Construction crews have milled the eastbound travel lanes, between Crescent Drive and Silver Avenue. Work is underway to place, mix, grade, and compact the subgrade prior to paving.

Manholes are being adjusted between Silver Avenue and Crescent Drive and damaged concrete drainage structures are being repaired or replaced as needed

image of workers paving Thomas DriveThe following photo shows crew members from Roberts and Roberts Inc. working to pave the outside shoulder of the Thomas Drive westbound travel lanes near the Hurt Street intersection.


Update: February 20, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive (i.e., the southern half of the four-lane roadway) are closed (as of Friday, Feb. 7) between Silver Avenue (near “the curve” on Thomas Drive) and the Biltmore Drive intersection. Two-way traffic (i.e., one lane in each direction) is being maintained on the northern half of the roadway.

Friday, Feb. 21, the lane shift will be extended four blocks west, from Biltmore Drive to Crescent Drive so that work may continue. Traffic will remain in this configuration for several weeks. The speed limit in the work zone (Joan Avenue to Silver Avenue) is reduced to 25 mph.

Construction activities

 Construction crews have milled the eastbound travel lanes (southern half of the roadway) to a depth of 11-inches between Silver Avenue and Biltmore Drive. Current work includes mixing, sampling and grading the soil in advance of applying eight-inches of lime rock base material. In addition, damaged underground drainage structures are being repaired or replaced

Friday, Feb. 21, the work zone will be extended four blocks to the west, from Biltmore Drive to Crescent Drive. Milling the existing asphalt, along with subgrade and base work is planned to start in this area Saturday, Feb. 22. Once the base work is completed crews will apply the structural lift of asphalt.

 image of the Milling work being done on the east bound lanes of Thomas DriveCrews from subcontractor Emerald Coast Milling work to mill the Thomas Drive eastbound travel lanes to a depth of 11-inches between Silver Avenue and Biltmore Drive.


image of soil stabilization work being done on the Thomas Drive resurfacing jobFollowing the milling activities, work begins to stabilize the soil for the eastbound travel lanes. To make room for the work, one lane of both east and westbound traffic is temporarily operating on the adjacent westbound travel lanes


image of Crews working beneath the roadway replacing damaged underground drainage structures.Beneath the roadway, crews work to repair/replace damaged underground drainage structures. In this photo, personnel from subcontractor L&R Contracting are shown modifying a drainage structure prior to installing a new concrete drainage pipe.


Update: February 13, 2020

Current traffic impacts

The eastbound lanes of Thomas Drive (i.e., the southern half of the four-lane roadway) are closed (as of Friday, Feb. 7) between Silver Avenue (near “the curve” on Thomas Drive) and the Biltmore Drive intersection. Two-way traffic (i.e., one lane in each direction) is being maintained on the northern half of the roadway. Traffic is expected to continue in this configuration for several weeks. The speed limit in the work zone is reduced to 25 mph.

Construction activities

The westbound lanes (northern half of the roadway) have been milled and resurfaced between Silver Avenue and Biltmore Drive. When paving was completed a traffic shift was implemented to allow work to begin on the eastbound lanes (southern half of the roadway). The week of Feb. 10, crews began milling the eastbound lanes to a depth of approximately 11-inches. Soil stabilization also began along with grading the work zone to a final template. When these activities conclude the contractor will place eight-inches of lime rock base prior to paving.

The first lift of asphalt is applied to the northern half of Thomas Drive (westbound lanes) between Silver Avenue and Biltmore Drive. Two-way traffic was subsequently shifted to these lanes so that milling and resurfacing work could begin for the southern half of the roadway (eastbound lanes). Crews are also removing and replacing damaged concrete drainage pipes and other structures beneath the roadway. The $8.1 million project will mill and resurface Thomas Drive between Bristol Street and Joan Avenue. Work is estimated for completion this summer.

Thomas drive paving image



Update: February 5, 2020

THOMAS DRIVE LANES TO SHIFT FRIDAY - Work continues on the Thomas Drive resurfacing and improvement project. On Friday, Feb. 7 construction crews plan to shift two-way traffic onto the westbound travel lanes, between Silver Avenue and Biltmore Drive, so that milling and resurfacing work can begin on the eastbound lanes.

Traffic is expected to remain in this configuration for the next several weeks. The Thomas Drive speed limit is reduced to 25 mph between Bristol Street and Joan Avenue. Work is currently estimated for completion this summer.


Update: January 24, 2020

Roadway work began Monday, Jan. 20 on the Thomas Drive resurfacing project. Crews are resurfacing and upgrading a 3.1-mile segment of Thomas Drive between Bristol Street and Joan Avenue. The $8.1 million project is funded by the county’s half-cent infrastructure surtax.

In addition to milling and resurfacing the roadway, this project will:
• Upgrade the drainage system.
• Make pedestrian improvements (additional mid-block crossings, apply new pavement markings).
• Widen bicycle lanes from four- to six-feet.
• Construct new trolley stop pull-off areas.
• Pave the parking lot at Rick Seltzer Park.

Current traffic impacts

The westbound lanes of Thomas Drive (i.e., the north half of the four-lane roadway) are closed between Silver Avenue (near “the curve” on Thomas Drive) and the Biltmore Drive intersection.

Two-way traffic (i.e., one lane in each direction) is being maintained on the south half of the roadway. Only right turns are allowed at the Silver Avenue, Spyglass Drive, and Biltmore Drive intersections.

The speed limit in the work zone is reduced to 25 mph. This traffic configuration will remain in place for several weeks

Construction activities

The contractor has removed the old asphalt from the westbound lanes beginning near Silver Avenue and continuing to near the Biltmore Drive intersection. Soil mixing is underway in this area for the new roadway subgrade. Samples of mixed material are being laboratory tested for compliance with specifications.

In the area that is closed to traffic, the team has also begun removing damaged drainage structures and installing a new pipe across Thomas Drive near Spyglass Drive.


1 MOT diversion - Silver to Biltmore 012020A lane shift is put in place Monday, Jan. 20 closing the Thomas Drive westbound lanes between Silver Street and Biltmore Drive. Two-way traffic (one lane in each direction) is being maintained using the eastbound travel lanes. This traffic configuration is expected to remain in place for several weeks.


DSC08464Construction crews work Wednesday, Jan. 22 to remove the asphalt from Thomas Drive westbound, between Silver Street and Biltmore Drive. The travel lanes will be reconstructed in this area and damaged portions of the underground drainage system will be repaired/replaced.

Overview

Roadway work began Monday, Jan. 20 on the Thomas Drive resurfacing project. Crews are resurfacing and upgrading a 3.1-mile segment of Thomas Drive between Bristol Street and Joan Avenue. The $8.1 million project is funded by the county’s half-cent infrastructure surtax.

In addition to milling and resurfacing the roadway, this project will:
• Upgrade the drainage system.
• Make pedestrian improvements (additional mid-block crossings, apply new pavement markings).
• Widen bicycle lanes from four- to six-feet.
• Construct new trolley stop pull-off areas.
• Pave the parking lot at Rick Seltzer Park.

Current traffic impacts

The westbound lanes of Thomas Drive (i.e., the north half of the four-lane roadway) are closed between Silver Avenue (near “the curve” on Thomas Drive) and the Biltmore Drive intersection.

Two-way traffic (i.e., one lane in each direction) is being maintained on the south half of the roadway. Only right turns are allowed at the Silver Avenue, Spyglass Drive, and Biltmore Drive intersections.

The speed limit in the work zone is reduced to 25 mph. This traffic configuration will remain in place for several weeks

Construction activities

The contractor has removed the old asphalt from the westbound lanes beginning near Silver Avenue and continuing to near the Biltmore Drive intersection. Soil mixing is underway in this area for the new roadway subgrade. Samples of mixed material are being laboratory tested for compliance with specifications.

In the area that is closed to traffic, the team has also begun removing damaged drainage structures and installing a new pipe across Thomas Drive near Spyglass Drive.

Contractors representing the Bay County public works department will begin work Monday, Jan. 13 to resurface a 3.1-mile section of Thomas Drive, between Bristol Street and Joan Avenue.

In addition to milling and resurfacing the pavement, the work will include:

  • Improving the drainage system
  • Widening bicycle lanes to six-feet.
  • Adding new mid-block pedestrian crossings, along with relocating and/or improving existing cross walks.
  • Updating pavement markings to improve pedestrian safety.
  • Designing/constructing new trolley stop pull-off areas.
  • Paving the parking lot at Rick Seltzer Park.
  • The $8.1 million project is funded by the county’s half-cent infrastructure surtax that was approved by voters in 2016.

The work is estimated for completion in mid-2020.

Construction procedures and impacts

Construction work will take place primarily during daytime hours. The contractor will, at times,close one-half of Thomas Drive an implement two-way traffic (one lane in each direction) on the remaining half of the roadway. Side street intersections may also be closed.


Drivers and bicyclists should expect temporary detours, lane shifts, and the potential for increased congestion during the project. Pedestrians may encounter sidewalk closures. Nearby residential and commercial properties may notice increased noise and dust from the construction activities, along with an increase in construction vehicle and equipment traffic.


Drivers should be alert for construction workers, vehicles, and equipment entering and exiting the roadway.

Staying informed

Stakeholders may contact the project team by telephone, (850) 724-3992; or by e-mail, info@ThomasDr.com.

To receive mobile text alerts, stakeholders can text the key word “ThomasDR” to 888-777.

 